CVAC Circumferential Road Construction
The last piece of the loop road around the Chesterfield Valley Athletic Center gets built for about $1.6 million, keeping vehicles away from players and participants.
I-64 & Long Road Interchange cost share
Council finalized the MoDOT cost share agreement and a $3.7M Lochmueller engineering contract (TDD-reimbursed) for the I-64/Long Road interchange, a project city leaders trace back to the 1998 valley transportation study.
Wilson Avenue Improvement Project
Residents packed in to support making the temporary road link permanent — it helps in bad weather and for emergency access. The city will design it (up to $40,000) and keep the temp connection meanwhile, pending Council approval.
Private street snow removal reimbursement
If a city snowplow or tree damages your mailbox, the city will now pay up to $500 instead of $300. Anything beyond that still means an insurance claim.
Public Street Acceptance — Estates at Conway (Harmony Court)
Harmony Court passed the city's inspection and is headed to City Council for acceptance as a public street, even though only two of the planned homes are built. Councilmember Tocco flagged past code violations and site issues during construction.
Public street acceptance – Harmony Court
Bill No. 3603 would make Harmony Court in the Estates at Conway a public city street, meaning the city would take over maintenance responsibilities there.
Elbridge Payne Road renamed to Mercy Way (proposed)
Mercy wants the street renamed Mercy Way for easier wayfinding, and the city is getting a plaque and the building renamed the Elbridge Payne Building to keep the history alive.
County arterial road maintenance transfer
St. Louis County may try to hand arterial road maintenance to cities, which could grow Chesterfield's road responsibilities by 20% and strain its budget. The committee wants a formal resolution opposing any unilateral move and encouraging other cities to join.
County arterial road burden on cities
The council was set to formally oppose St. Louis County shifting responsibility — and costs — for arterial roads onto municipalities.
Wildhorse Village street acceptance and snow removal
The city is preparing to take over Wildhorse Village streets, which are currently damaged by construction. A contractor, BSR, will plow them because the tight layout doesn't fit city equipment — and the Special Business District pays the bill.
Concrete Slab and Sidewalk Repairs
The annual pavement report shows the city is tracking its concrete streets with data-driven inspections. Funding for replacements dips below $4 million in 2027, and the committee may add money during budget deliberations.
Snow and Ice Salt Supply
The city locked in 3,000 tons of road salt for winter at $98.90 a ton through the regional cooperative — within budget.
Swingley Ridge Road project funding
A bill committing partial city funding for the North Outer 40 – Swingley Ridge Road project had its first reading. A final vote comes later.
Hog Hollow Road closure engineering
The council hired Horner and Shifrin for up to $115,000 to handle engineering for the Hog Hollow Road closure, drawing from general fund reserves.